Our 7 Day Process

DAY 1

  • Remove shower screen/taps/shower rose
  • Remove 1-2 rows of wall tiles for a base repair or full walls upto shower rose for a full repair.
  • Remove walls linings/cement render to wall
  • Remove hob tiles, top & inside
  • Remove floor tiles & floor bed
  • Inspect for further damage & report

DAY 2

  • Render/reline walls where required
  • Apply a coat of Epoxy waterproofing, which is part 1 of our seamless flexible membrane, to shower with upturns to walls & over hob dressing down into the drain.

DAY 3

  • Apply 1st coat of hybrid waterproofing membrane to shower with upturns to walls & over hob dressing down into the drain.

DAY 4

  • Apply 2nd coat of hybrid waterproofing membrane to shower with upturns to walls & over hob dressing down into the drain.

DAY 5

  • This is curing day so no attendance on site.

DAY 6

  • Supply & fix wall tiles as needed to walls & hob areas.
  • Supply & fix floor tiles inc new waste
  • Grout tiled area

DAY 7

  • Re-install existing showerscreen
  • Clean up site and hand over to the client