Our 7 Day Process
DAY 1
- Remove shower screen/taps/shower rose
- Remove 1-2 rows of wall tiles for a base repair or full walls upto shower rose for a full repair.
- Remove walls linings/cement render to wall
- Remove hob tiles, top & inside
- Remove floor tiles & floor bed
- Inspect for further damage & report


DAY 2
- Render/reline walls where required
- Apply a coat of Epoxy waterproofing, which is part 1 of our seamless flexible membrane, to shower with upturns to walls & over hob dressing down into the drain.
DAY 3
- Apply 1st coat of hybrid waterproofing membrane to shower with upturns to walls & over hob dressing down into the drain.


DAY 4
- Apply 2nd coat of hybrid waterproofing membrane to shower with upturns to walls & over hob dressing down into the drain.
DAY 5
- This is curing day so no attendance on site.
DAY 6
- Supply & fix wall tiles as needed to walls & hob areas.
- Supply & fix floor tiles inc new waste
- Grout tiled area
DAY 7
- Re-install existing showerscreen
- Clean up site and hand over to the client